Használati útmutató Speco Technologies SXU24V
Olvassa el alább 📖 a magyar nyelvű használati útmutatót Speco Technologies SXU24V (2 oldal) a nincs kategorizálva kategóriában. Ezt az útmutatót 14 ember találta hasznosnak és 7.5 felhasználó értékelte átlagosan 4.6 csillagra
Oldal 1/2

®
Install Guides
SXU24V
STEP 1
1. Check to ensure that all breakers are in the “OFF” position
before connecting any wires to the terminal blocks.
Mounting
the Enclosure
The SXU and SXA enclosures are designed
to be mounted to a wall or pole. The
enclosure utilizes an integrated mounting
plate on the back.
U-bolt
Hose Clamp
Lag Bolt
Install Guide
Mounting the enclosure
UPS Backup Kits
The AL2 and AL5 enclosures are designed to be mounted
to a wall or pole. The AL2 utilizes an integrated mounting
plate on the back of the enclosure.
The AL5 Enclosure comes integrated with Unistrut attached
to the back of the enclosure, and can be mounted usin
any applicable unistrut mountin hardware found at
most hardware stores.
AL2 Enclosure
AL5 Enclosure
Phone : + (208) 904-04244774 South Hwy 191, Rexburg, ID 83440 E-Mail : support@vorpenergy.com
Unistrut
Rear of AL5 Enclosure
WIRING
Wiring the UPS backup Kit
Check to ensure that all breakers are in the “OFF” position
before connecting any wires to the terminal blocks.
Step 1
Step 2
Phone : + (208) 904-0424
4774 South Hwy 191, Rexburg, ID 83440
E-Mail : support@vorpenergy.com
Cable Gland
- If your part # ends with -12, connect your two 12 Volt Batteries in parallel to keep the battery voltage at 12VDC.
- If your part # ends with -24, connect your two 12 Volt Batteries in series to create a 24VDC Battery Bank.
Step 3
Ensure that the Voltage Selector Switch is set to the appropriate
Voltage. (Located to the Left of AC Input on Battery Charger)
- 115 VAC (90 to 132 VAC) *Slide Switch Towards Faceplate
- 230 VAC (180 to 264 VAC) *Slide Switch Away From Faceplate
Step 4
Passing through the provided cable gland, connect the AC power to
the AC Battery Charger using the provided butt connectors.
Step 5
Connect 12/24 VDC Equipment to the green phoenix terminal on the
faceplate. Connect any IP Equipment to the provided PoE Injectors
mounted on the DIN rail
Step 6
Power up the system by first powering the Battery Charger with the
ON/OFF switch located behind the AC Input. Then flip Breaker 1
followed by Breaker 2.
Parallel Connection Series Connection
Voltage Selector Switch
ON/OFF Switch
AC Input
Phoenix Terminal
*In cold climates SLA batteries require insulation
Wiring the UPS backup Kit
Check to ensure that all breakers are in the “OFF” position
before connecting any wires to the terminal blocks.
Step 1
Step 2
Phone : + (208) 904-0424
4774 South Hwy 191, Rexburg, ID 83440
E-Mail : support@vorpenergy.com
Cable Gland
- If your part # ends with -12, connect your two 12 Volt Batteries in parallel to keep the battery voltage at 12VDC.
- If your part # ends with -24, connect your two 12 Volt Batteries in series to create a 24VDC Battery Bank.
Step 3
Ensure that the Voltage Selector Switch is set to the appropriate
Voltage. (Located to the Left of AC Input on Battery Charger)
- 115 VAC (90 to 132 VAC) *Slide Switch Towards Faceplate
- 230 VAC (180 to 264 VAC) *Slide Switch Away From Faceplate
Step 4
Passing through the provided cable gland, connect the AC power to
the AC Battery Charger using the provided butt connectors.
Step 5
Connect 12/24 VDC Equipment to the green phoenix terminal on the
faceplate. Connect any IP Equipment to the provided PoE Injectors
mounted on the DIN rail
Step 6
Power up the system by first powering the Battery Charger with the
ON/OFF switch located behind the AC Input. Then flip Breaker 1
followed by Breaker 2.
Parallel Connection Series Connection
Voltage Selector Switch
ON/OFF Switch
AC Input
Phoenix Terminal
*In cold climates SLA batteries require insulation
STEP 2
1. If your part # ends with -12V,
connect your two 12 Volt
Batteries in parallel to keep
the battery voltage at 12VDC.
2. If your part # ends with -24V,
connect your two 12 Volt Bat-
teries in series to create
a 24VDC Battery Bank.
U-bolt
Hose Clamp
Lag Bolt
Install Guide
Mounting the enclosure
UPS Backup Kits
The AL2 and AL5 enclosures are designed to be mounted
to a wall or pole. The AL2 utilizes an integrated mounting
plate on the back of the enclosure.
The AL5 Enclosure comes integrated with Unistrut attached
to the back of the enclosure, and can be mounted usin
any applicable unistrut mountin hardware found at
most hardware stores.
AL2 Enclosure
AL5 Enclosure
Phone : + (208) 904-04244774 South Hwy 191, Rexburg, ID 83440 E-Mail : support@vorpenergy.com
Unistrut
Rear of AL5 Enclosure
OFF
Termékspecifikációk
| Márka: | Speco Technologies |
| Kategória: | nincs kategorizálva |
| Modell: | SXU24V |
Szüksége van segítségre?
Ha segítségre van szüksége Speco Technologies SXU24V, tegyen fel kérdést alább, és más felhasználók válaszolnak Önnek
Útmutatók nincs kategorizálva Speco Technologies
19 Március 2025
28 December 2024
28 December 2024
19 Szeptember 2024
19 Szeptember 2024
19 Szeptember 2024
18 Szeptember 2024
4 Szeptember 2024
3 Szeptember 2024
3 Szeptember 2024
Útmutatók nincs kategorizálva
- nincs kategorizálva Aeris
- nincs kategorizálva ORNO
- nincs kategorizálva CAD Audio
- nincs kategorizálva Wet Sounds
- nincs kategorizálva Oben
- nincs kategorizálva Blackburn
- nincs kategorizálva Rexel
- nincs kategorizálva Swiss Eye
- nincs kategorizálva Hard Head
- nincs kategorizálva Powertec
- nincs kategorizálva Ergotron
- nincs kategorizálva ETC
- nincs kategorizálva SmallRig
- nincs kategorizálva Expressive E
- nincs kategorizálva Hagor
Legújabb útmutatók nincs kategorizálva
10 Április 2025
10 Április 2025
10 Április 2025
9 Április 2025
9 Április 2025
9 Április 2025
9 Április 2025
9 Április 2025
9 Április 2025
9 Április 2025